NOTICE
To: All Greens Residents
Date: APRIL 19, 2011
As a part of the upcoming community repair and improvement program, contractors will commence concrete and asphalt repairs beginning this week which we anticipate being completed next week. Additional notices will follow regarding the scope and timing of the additional improvement projects that will commence in the near future.
The initial road repair program will occur this and next week and will be comprised of
1) Storm Drain Collar Replacement and 2) Asphalt Repairs:
Storm Drain Collar Replacement
a. The badly damaged concrete collars surrounding the storm drains in the community will be removed and replaced.
b. This work will Commence Thursday, April 21, 2011, and will be completed the same day.
c. The areas will be roped off with construction tape, cones and barricades while the concrete cures for twenty-four (24) hours following construction. Access should not be impeded to the community or driveways.
d. Please take extra care not to hit the cones or barricades and do not remove same as it is critical that the concrete is able to cure correctly, otherwise the Association will incur additional expense to repair this work.
Asphalt Repairs
a. There are areas of degraded asphalt throughout the community. These areas will be removed and patched with new asphalt.
b. This work will commence Wednesday, April 27, 2011 or Thursday, April 28, 2011 and will take approximately two (2) days to complete.
c. There will be minimal impact to access and traffic while the repairs are being conducted.
d. The new asphalt will be ready for traffic the same day it is installed.
Seal Coating will commence at a later date.
If you have any questions, or concerns, please don’t hesitate to contact Andrew at manager@demamgt.com, or 305-766-8415.